The company has experienced nearly 40 years of its establishment and development. All its staffs and workers have made great efforts to make TASCO an asserted and reputable brand in the construction and erection market, and this brand has made a good hallmark on a number of large-scale projects of the country. Typical projects have been completed by TASCO include:

The company has experienced nearly 40 years of its establishment and development. All its staffs and workers have made great efforts to make TASCO an asserted and reputable brand in the construction and erection market, and this brand has made a good hallmark on a number of large-scale projects of the country. Typical projects have been completed by TASCO include:

NO

Projects

Total value (1,000 VND)

Construction value accepted (1,000 VND)

Duration

Owners

Commencement

Completion

1

Road D3 + D4 Hoa Xa Industrial Park – Nam Dinh city

30,930,443

30,930,443

01/2003

07/2004

Industrial Park Infrastructure Development Company

2

Project CP3- on drainage for Van Cao road – Nam Dinh city

10,708,000

10,708,000

10/2005

02/2006

WB PMU of Nam Dinh city

3

Building the infrastructure for Phu Giay Temple – Vieng market complex – Vu Ban district – Nam Dinh province

18,072,389

18,072,389

12/2005

05/2006

People’s Committee of Vu Ban district

4

Ring road in the Northeast of Nam Dinh city (road section connecting the old National highway No. 10 to the New Highway)

13,098,204

13,098,204

01/2006

06/2007

Transport PMU of Nam Dinh city

5

Improvement and upgrade of the provincial road No. 51B from National highway No. 21 to Quat Lam eco-Resort – Giao Thuy district

67,947,000

67,947,000

06/2005

09/2007

People’s Committee of Giao Thuy district

6

Road from Bui bridge – Doc Loc – Nam Dinh city

13,865,642

13,865,642

01/2006

12/2007

People’s Committee of Nam Dinh city

7

Package No. 4: Road + sidewalk + drainage system from Km4+680-Km6+669,45 under the construction of North-South trunk road

19,343,078

19,343,078

06/2007

03/2008

Urban Transport Management Unit 4 – Transport Department of Ho Chi Minh City

8

Package No. 3: Km18-Km25+380 – the project on improvement and upgrade of National highway No. 70

24,152,000

24,152,000

01/2008

01/2009

PMU 5

9

Package NIP/CP3 on improvementand upgrade of National highway No. 48-2, section Yen Ly – Nghia Thuan

28,788,968

20,774,000

01/2006

2008

PMU 18

10

3 bridges in Nghe An province ( including Nam Ton bridge, Khe Da bridge, Thung Heo bridge)

17,381,210

17,381,210

08/2007

12/2008

Nghe An Transport PMU

11

An Dong road (phase 1) in Nam Dinh province

25,306,000

25,306,000

10/2007

2009

People’s Committee of Hai Hau district, Nam Dinh province

12

Road on the left bank of To Lich river – Hanoi

55,886,064

15,141,000

2007

2009

Drainage PMU

13

National highway No. 28 Section Gia Nghia - DakNong

45,921,783

17,348,218

01/2007

03/2009

Ho Chi Minh Road PMU

14

Drainage channel No. 3 – Viet Hung new urban area – Gia Lam – Hanoi

14,773,601

14,773,601

3/2004

12/2004

Housing and Urban Development Investment Corporation

15

Handling unexpected problems to recover consequences caused by Hurricane No. 7 for the Sea Dyke – Nam Dinh province

24,784,070

24,784,070

10/2005

4/2006

Nam Dinh province

16

Embankment of Thinh Long beach

11,009,224

11,009,224

4/2006

07/2006

People’s Committee of Hai Hau district

17

Nam Thinh embankment, Thai Binh province

10,200,000

10,200,000

1/2007

05/2007

Thai Binh Department of Agriculture & Rural Development

18

Fishing port at berth area for tropical storm protection for Ninh Co estuary – Hai Hau district - Nam Dinh province

39,307,354

39,307,354

9/2005

12/2007

Nam Dinh Department of Fisheries

19

Package No. 3: consolidating, protecting and upgrading sea dyke No. 5 from K24+400-K26 under the project on consolidating, protecting and upgrading sea dyke No. 5 from K24-K26 Tien Hai district – Thai Binh province

15,128,411

15,128,411

1/2008

07/2008

PMU of Thai Binh Department of Agriculture & Rural Development

20

Tay Thanh Nien dike dam – Ang Giao Phong

14,392,118

14,392,118

7/2008

2009

PMU for Natural Disaster Recovery 2005 of Nam Dinh province

21

Construction, supply and installation of construction equipment and plants in the Eastern line of the indoor Athletic Competition Palace (extended road section from Nguyen Co Thach road)

32,575,803

32,575,803

2009

2009

PMU for investment projects of State-funded construction works

 